In progress

rozbudowa_mlekpol

Expansion of the sewage treatment plant at the Mlekpol dairy plant

Inwestor:MLEKPOL

Lokalizacja: Grajewo

Zakres prac: Construction of an anaerobic sludge treatment installation, gas engine installation and sewage sludge drying installation

plik SUW

Expansion of the sewage treatment plant at the Turów Power Plant

Inwestor: PGE GiEK S.A. Power Plant Turów

Lokalizacja: Bogatynia

Zakres prac: Turnkey expansion of industrial wastewater treatment plants based on membrane microfiltration and reverse osmosis technologies as well as chemical precipitation of sulphates

plik SUW

Autothermal oxygen hygienization installation of sewage sludge ATAD at the sewage treatment plant in Kolno

Inwestor: Przedsiębiorstwo Usług Komunalnych Sp. z o.o.

Lokalizacja: Kolno

Zakres prac: Delivery, assembly and start-up of the ATAD installation

plik SUW

Modernization of the wastewater treatment plant in Dairy Plant POLMLEK

Inwestor: POLMLEK Sp. z o.o.

Lokalizacja: Lidzbark Warmiński

Zakres prac: Turnkey modernization of the wastewater treatment plant, including: preliminary wastewater treatment system, chemical pre-treatment system, biological reactor with auxiliary installations, cogeneration units, sludge dewatering unit and secondary sedimentation tank

plik SUW

Modernization of the wastewater treatment plant in Power Plant Połaniec

Investor: ENEA Elektrownia Połaniec S.A.

Location: Połaniec

Scope of work: Design, supply, assembly and start-up of technological devices, including decanter centrifuges, lamella separator, hydrochloric acid dosing station and sodium hypochlorite dosing station.

plik SUW

Modernization of the wastewater treatment plant in PEC Gliwice

Investor: Przedsiębiorstwo Energetyki Cieplnej - Gliwice Sp. z o.o.

Location: Gliwice

Scope of work: Implementation in the turnkey system of modernization of industrial wastewater treatment plants in order to adjust the quality of wastewater to the requirements contained in BAT conclusions based on technologies for the removal of heavy metals and sulfates, wastewater recarbonisation and final filtration.

plik SUW

Hydrolysis and fat pasteurization installations at a wastewater treatment plant in Zielona Góra

Investor: Zielonogórskie Wodociągi i Kanalizacja Sp. z o.o.

Location: Zielona Góra

Scope of work:Delivery, assembly and commissioning of the Aerotherm hydrolysis installation and fat pasteurization installation for the Zielona Góra agglomeration

plik SUW

Construction of water cooling system at ANWIL S.A.

Investor: ANWIL S.A.

Location: Włocławek

Scope of work: Design, delivery of equipment and construction in the EPC formula of the water cooling system on the premises of ANWIL S.A. in Włocławek based on a cooling tower, pumping station, filtration processes and water conditioning.

plik SUW

Water demineralization plant

Investor: Large chemical plant

Location: Poland

Scope of work: Design, supply and turnkey implementation of a water demineralization installation, including a new demineralized water station based on membrane technologies, a new ion-exchange water demineralization line and power supply for 6/0.4 kV transformers.

plik SUW

Hydrolysis and fat pasteurization installations at a wastewater treatment plant in Zielona Góra

Investor: Zielonogórskie Wodociągi i Kanalizacja Sp. z o.o.

Location: Zielona Góra

Scope of work:Delivery, assembly and commissioning of the Aerotherm hydrolysis installation and fat pasteurization installation for the Zielona Góra agglomeration

plik SUW

Wastewater Treatment Plant in Łękińsko and Kleszczów

Investor: Kleszczów Commune

Location: Kleszczów Commune

Scope of work: Expansion of the sewage treatment plant in Łękińsko together with the reconstruction of the sewage treatment plant in Kleszczów, construction of a sewage pressure pipeline from the sewage treatment plant in Kleszczów to the sewage treatment plant in Łękińsko and construction of a Selective Municipal Waste Collection Point.

plik SUW

Modernization of Northern Water Treatment Pant

Investor: MPWiK w m st. Warszawie S.A.

Location: Wieliszew

Scope of work: Construction of intermediate ozone and carbon filters installation with capacity adjusted to the current and forecasted production of the Northern Plant.

Używamy plików cookies, aby dostosować pokazywane treści do Twoich zainteresowań. Brak akceptacji stosowania plików cookies może ograniczyć funkcjonalność strony i dostępność niektórych informacji.